Construction of the exit from the Podilskyi-Voskresenskyi bridge to Troeshchyna. The final stage

image

At the final stage of the construction of a 90-meter road tunnel under the railway tracks. Autostrada specialists installed the frame and formwork of the floor slab. We start concreting. In a week, when the concrete will gain strength, we will install the insulation and start the sampling of soil and the construction of the road inside the tunnel. The construction of the tunnel takes place in 2 stages so as not to stop railway traffic.
An elevated platform, stairs and ramps were built for the comfort of passengers at the Raiduzhny station (Troyeshchyna-2).
The construction of the road from St. Peter Vershigory to the tram ring. Sidewalks, bike paths, a storm sewer system, retaining walls and noise barriers have been installed. Currently, the Autostrada road crews are building the road to the tunnel from the side of the Rusaniv Gardens.
Understanding the importance of opening the Podilsk-Voskresensky bridge for all types of transport, we work at the facility around the clock.